MF50 is does the cacapcity leveling based on mateail -run schedule order (planned order ) where as in discrete manufacturing , when you run the MRP , MRP system assume Infinite Capacity and schedule the order as per your selection in MD02(2,1,3,3,2) and then you convert those planned order to Production order .Here you checkied the Capacity in Production Order level .
In stanadrd SAP , it is not possible to use MF50 for discrete production order.
In discrete order or process order , do the caapcity leveling , there are seperate planning table available based on Over all Capacity Profile and Schedule type .This can be done in following way :
1.CM31-Production Order Wise -Tabular
2.CM23-PO wise -Graphical
3.MC88: Ruf Cut Planning
Work Centre Wise : CM21 -Graphical , CM22-Tabular Planning Table .
Make sure the below set up before you carry on the Capacity leveling :
.Define time profile in OPD2.
Define the strategy profile in OPDB
Define the Overall profiles in OPD0.
In OPJK maintained check capacity with SAPSFCG013 profile for your production order type
In OPU3 , scheduleing parametre s: Generate Capacity , Scheduling Type , Automatic Log ,Start date in Past as per your req.
In OPJU , chekc the contol tab of the scheduleing as per OPU3
In OPKP- Production scheduling paranmeters assing the overall capacity profile -SAPSFCG013 with finte scheduling tick.
Master Data :
1.Materials Master define the Production scheduler and production scheduling profile
2.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
3.Routing - enter the values for the standard values. Use control key with scheduling.
Hope this will help you .